1 Base game as it arrived.
2
3
4
5 Teardown begins.
6 Hand picked replacement playfield getting some slight corrections and being prepped for clear.
7 Cleared.
8
9 Shooter lane corrected and extremely nice in terms of wood as well as layer graduations.
10
11 Will continue the restore while this cures.
12 Playfield is cured and ready to sand and prep for the final clear,
13
14
15 Final clear applied.
16
17 Shooter lane is even smoother now.
18
19 That is it for the clear.
20 Moving on to the freshly built new cabinet.
21
22 Cabinet will be prepped for refinishing next.
23 Lower prepped and masked for priming.
24 Lower primed and and guide coated.
25 Apron is being repaired.
26
27 Apron cleared.
28
29
30
31 Teardown is nearly complete.Will go straight into rebuild once all parts are serviced.
32 Playfield rebuild in process.
33
34
35
36
38
39
40