81 Trim installed.
82
83 Will rework the coindoor now.
84
85 Coin door gutted.All parts will be gone through.
86 Coin door refinished factory style.
87 Some of the inner backbox wiring needs work. Most of the burning is GI related.
88 Connector rebuilt.Now as two individual ones so I can separate the GI from the flasher wiring for simplicity .The translate
89 GI connector at the board.
90 GI connector rebuilt.
91 Driver board has been serviced.
92 Will rework the DMD panel now
93 Stripped,lightly refinished.
94 Rebuilt with a new window and upgraded speakers.
95 Panel is complete.
96 Boards and cabinet wiring in place.
97 All wiring neatly run,metal polished etc.A new sheet will be installed later.
98 Cabinet rebuild complete.
99 Rebuilt coin door installed.Cabinet is now ready for the playfield assembly.
100 Supplied red ramps are being built.
101 Ships refinished.
102 Playfield is ready to complete topside then drop into the cabinet.
103
104
105
106 New plastic set.
107 Playfield build is complete and now in the cabinet.
108
109
110
111
112
113
114
115 Game is complete less a little detailing like installing the cabinet sheet and translite panel.
116 Translite panel is rebuilt.
117 Game is complete.
118
119