Starting platform is quite a bit rougher than it appears at a first glance.
|
2
The cabinet touch ups were done right over the bolts.
|
3
The top of the back of the head is swollen from som moisture exposure.Replacement will be the best course of action on that.
|
4
the playfield is okay.Typical insert bordering and chipping but overall it is just very dirty.
|
5
|
6
The inside of the cabinet is pretty wrecked.The metal is well corroded and it is of course filthy.
|
7
The underside playfield matches the inside of the cabinet.
|
8
Someone has hacked straight into the transformer so that will have to be checked into.Most likely it will just need new male
|
9
DmD panel is nice and looks like new.The lamp panel will need to be torn down and refinished.
|
10
all the boards and wiring in the head are filthy but besides the typical GI connector burn they all look fine.
|
11
Head is gutted.
|
12
Playfield teardown in process.
|
13
|
14
|
15
Playfield is out of the game and stripped bare including the t nuts.
|
16
Now that it is completly torn down I can see some very heavy ball tracks in the loops that may have to be repainted if they
|
17
Cabinet tear down in process.
|
18
Cabinet disassembly is basically complete.I will just need to remove the old siderails prior to begining the repairs.
|
19
|
20
The head was really prett solid aside for the water damage at the top of the back.Since I now have my own screen to redo t
|
21
I am using a nice birch for replacement.Not doubt this is a good upgrade compared to the mdf used at the factory.
|
22
I have clamped the old to the new for hole alignment.
|
23
All the holes have been drilled and dimpled.
|
24
The head is placed on the ground so it will have a nice solid backing while I replace and tap the new wood in place.
|
25
New panel is glued and nailed in place.Just a few finish nails are used in key spots to hold everything tight will the glue
|
26
Head is back in solid condition..
|
27
The chocks are re-intalled.
|
28
Head is ready to strip and repair.
|
29
Head is back down to bare wood.
|
30
Lower cabinet is ready to strip and repair.
|
31
Some poorly done previous repairs will have to be redone.
|
32
Front is stripped bare.
|
33
Lots of repair work is needed in the back of the cabinet.The chocks will also be replaced.
|
34
the bottom has been freshened up to remove the light moisture swell.It was very minor and just more of a film than anythin
|
35
|
36
Sides stripped to bare wood.
|
37
Cabinet is stripped down to bare wood all the way around now and is ready to begin filling.
|
38
Considering the fact that some of the structure of the cabinet is a little rough around the legs and the lip of the cabin
|
39
The initial filler is applied to the worst areas.
|
40
The old repairs were trenched out and are being redone to ensure a good solid bond and proper adhesion.
|